This brand-new landmark campus in the heart of Barry will provide a vibrant place to learn for the whole community. Open throughout the week, including evenings and weekends, the Barry Waterfront Campus will provide a learning environment for people of all ages, from young school leavers to adults. More than just traditional classrooms, the campus will be home to real-world learning and state-of-the-art learning spaces such as a Hair and Beauty Salon and a Restaurant that will both be open to the public, giving learners hands-on experience while creating welcoming spaces for the local community to enjoy.

Light, modern teaching and IT rooms will sit alongside social spaces including a courtyard with lawn seating, an external garden terrace and a covered outdoor dining area — places to take a break, meet friends or simply enjoy being on campus.

Latest Progress

We’re sharing regular updates on the construction of our two new Cardiff and Vale College campuses in the Vale of Glamorgan. Check back here to see the latest progress, including key milestones and drone footage.

October 2026

Weather tightness has been achieved, and internal fit-out has commenced on all levels. Work is continuing in the plant room, while roofing is complete and cladding has commenced at roof level. Brickwork is ongoing across five elevations.

In the coming period, the high- and low-voltage plant will arrive on site. Brickwork will be completed on key elevations to allow scaffolding to be removed, and roof cladding works will be completed. Ground works will continue in the car park, alongside internal fit-out throughout the building. Screeding is planned for the floor levels, and fit-out of the atrium is due to commence.

September 2026

The structural phase is now complete with steel framing and concrete slabs finished. Our façade team is in full swing, with brickwork set to begin this September. Internal fit-out works are already underway and will continue through the coming months.

Forthcoming construction

Our focus shifts to the exterior envelope with ongoing brick façade and curtain walling installation, alongside roof completion. Interior construction will progress in parallel across all areas of the site.

July 2026

Project Overview

Construction at Barry Waterfront Campus, Cardiff & Vale College, is advancing well with concrete works nearing completion and focus transitioning to structural envelope and interior systems preparation.


Progress to Date

  • Structural Works: All upper floor slabs completed; ground floor slab progressing with 4 of 5 planned pours finished
  • Envelope Systems: Structural facade systems (SFS) and window installation underway on Phase 1
  • Site Infrastructure: Groundworks progressing in car park and northern project areas
  • Roof Systems: Plant room and main roof installation ongoing


Upcoming Works

  • Ground floor slab completion (final pour)
  • Phase 1 SFS completion and continued window installation
  • SFS installation across all remaining elevations
  • Commencement of internal trade works (mechanical, electrical, plumbing, etc.)

The project is progressing smoothly across multiple work streams, with the transition from structural and envelope works to interior fit-out expected in the coming weeks.